Construction Notice

News 0 Comments

Helena Sand & Gravel will be starting Phase III of the Front St Project starting on September 3rd. This will consist of working on Neill Avenue, from Last Chance Gulch to Front Street. This work will be completed over the next 3 months. Construction includes, new storm drains with manholes, curb and gutter, sidewalks, landscaping, and asphalt paving.
During the construction process, Neill Avenue will be closed from Fuller Avenue to Last Chance Gulch. Fuller Avenue will remain open with the potential of being closed starting the week of September 30th. Neill Avenue will be closed to thru traffic with local traffic allowed. Access for local residence and business will be maintained during construction. Please be cautious and obey all traffic signs and personnel.

Construction is scheduled to begin September 3rd 2019.

Phase III will consist of work starting at the intersection Neil Avenue and Front Street heading east on Neil for approximately 300'. The work will consist of: 60" storm drain installation with manholes, asphalt patching

Phase III is scheduled to start September 3rd. Weather depending HSG expects the project to be substantially complete by early December. Chip sealing, final striping, and landscaping will be completed in late Spring of 2020.

Work is currently scheduled to take place Monday-Friday, with some Saturdays scheduled, 7am to 7pm. For your safety and the safety of our crews, we ask you to use extreme care when in or around the work area.

If you have any questions or concerns please contact us between the hours of 7:00 am and 6:00 pm.

Project Manager: Solomon Redfern 406-459-2003

Thank you
Helena Sand & Gravel, Inc.